2023

  • Hot tubs were replastered and tiled

  • Replaced pool furniture

  • Purchased two new firepit areas

  • Replaced pool lights

  • Installed cameras in garage

  • Replaced pool fence

  • Replaced packing in west elevator

  • Planted new garden behind hot tubs

  • Replaced exterior stairwell lights

  • Replaced pool sand filter

  • Replaced hot tub furnace

  • Repaired south sprinkler system

  • Repaired drainage in garage

  • Repaired heat tape in Phase 2

  • Replaced carpeting in elevator cabs and landings

  • Pressure washed and re-striped garage

  • Replaced hot tub covers and pool cover reel

  • New flower planters above entrance driveway

  • Aphid infestation was successfully remedied

  • Unit fireplace thermostats were replaced with timers

  • Created new HOA website

  • Created new phone system

2022

  • Replaced dry fire sprinkler system for garage

  • Installed new back flow system

  • Exterior building repairs completed around tall dining room windows

  • Ceiling repairs in housekeeping closet completed

  • Trees removed by hot tubs and center pool entrance

  • Created mail/package room

  • New pool pump assembly installed

  • Vibration monitors installed in garage

  • Snow melt system repaired

  • Replaced east elevator motherboard

  • Installed well for watering at north end of building

  • Repaired center easement stairs

2021

  • Repainted building

  • Repaired and repainted railings

  • Replaced outdoor carpeting

  • Installed new unit doors and hardware

  • Replaced heat tape in garage and repainted garage ceiling

  • Flower boxes – purchased, primed, painted and decorated

  • Installed hand sanitizer dispensers on every floor and in garage by elevators

  • Resolved/repaired east elevator grounding issue

  • Repaired drainage piping and floor near unit 104

  • Upgraded lighting in storage and maintenance areas with LED

  • Made concrete repairs on balconies and garage area

  • Installed 450 snow clips

2020

  • Phase 1 heat tape replaced in garage

  • Pool and Spa Major Repairs

    • Pool and hot tub crushed pipes were excavated and repaired

    • Snowmelt system was drained and repaired

    • Electrical system for pool lights was rewired

    • Pool circulatory pipes were replaced

    • Hot tub motor was replaced

    • Pool room electrical outlets replaced to be GFCI compliant

    • Pool room flow meters were replaced

    • Hot tub emergency shutoff buttons replaced

  • Installed flower boxes along interior walkways

  • Replaced roof clips on southwest side of building

  • Dry fire sprinkler repairs identified during regular inspection were made

  • Replaced all GFCI outlets in garage

  • Replaced drains by Unit 104 and repaired floor to resolve standing water and flooding issues

  • Replaced existing laundry equipment and installed 5 new washers and dryers with electronic payment devices and laundry app

  • Installed hand sanitizer dispensers on all floors by elevators

2019

  • Pool changing rooms and bathroom renovation

  • West elevator traveling cable replace and new heater installed

  • West elevator motor replaced

  • New circuit panel in west laundry room

  • New circuit panel behind office

  • East hot tub motor, jet pump and sensor were replaced

  • New hot tub covers

  • Pool furnace circuit panel that has been repaired

  • Pool circulator pump replaced

  • South lawn irrigation complete after parking lot tear-down

  • New courtyard furniture

  • New pool & garage signage

2018

  • Garage renovation

  • Refaced ski lockers

  • Replaced old wood with hardie-board

  • Garage painting – walls and ceiling

  • New ceiling tiles in elevator landings

  • Cleaned and restriped garage floor

  • New ADA ramp at west elevator

  • Replaced lighting with LED

  • New signage

  • Installed LED lighting in elevators, laundry rooms, office, and maintenance shop

  • Motion sensors installed in laundry rooms and changing rooms

  • Renovated both laundry rooms

    • New flooring

    • Painted

    • Updated plumbing

    • New folding tables and garment racks

  • New carpeting in both elevators and garage level landings

  • New southeast irrigation

  • New pool furnace

  • New pool loungers, tables and umbrellas

  • New unit signage on each floor by west elevator

2017

  • New carpeting in both elevators and garage level landings

  • Comcast Xfinity bulk account

  • New signage in garage

  • New gutters on east stone veneer

  • Snow clips above 113-116

  • New gutter and heat tape above 602-604 area

  • New south area garden

  • New lighting on the south sidewalk

  • New hot tub covers

  • Exterior stairwells were resurfaced

  • Interior stairwells lighting was replaced with LED lighting

  • New flower company – Dragonfly Gardening

  • New keyless entry hardware on all unit doors

2016

  • Stone Veneer on East and South sides of Vantage Point-Vail

  • Renovated office

  • New bike racks that are removed during ski season to create more parking spaces

  • Three new luggage carts

  • Electric car charging station

  • Unit door hardware updating

    • Consistency throughout building

    • Security

  • Pool & hot tubs are up to code with safety equipment

  • Replaced fluorescent lighting with LED outside the unit doors

  • Stairwell lights are being replaced with LED lighting when they burn out

  • New signage for the office and west laundry door

  • Elevator signage is now up to code and new matts were installed

  • Stairwells were pressure washed

  • New drain and replacement of existing drains on 1st floor SE stairwell that were full of silt

  • New carpeting in both elevators and garage level landings

2015

  • Installed new entrance sign

  • Installed pet station

  • Office remodeled

2014

  • Painted exterior of building and railings

  • Resurfaced the decking

  • Refurbished both spa

  • Installed 9 new lamp post light fixtures throughout the properties

  • Replaced old timbers with a boulder retaining wall

  • Replaced all common door hardware with ADA compliant hardware

2013

  • Phase I elevator replaced

2012

  • Replaced all outdated smoke/heat detectors in all units that were older than 10 years

  • Installed speed bumps in garage

2011

  • Phase II elevator upgraded and renovated

  • Building cable was rewired

  • Replaced concrete walkway ramp on the south side of building

  • Repaired concrete walkway “T”s in Phase II

  • Completed major repairs to east spa

2010

  • Painted exterior building including garage and garage ceiling

  • Replaced garage lighting with new fixtures

  • Upgraded the fire alarm system with a new control panel and unit detectors

2009

  • Installed carbon-monoxide detectors in all units

  • Repaired cracked walls in garage

  • Both laundry rooms flooring was replaced and hung ceilings installed

  • Replaced asphalt paving in the south side of garage

  • Constructed the dumpster enclosure room

2008

  • Replaced 350 feet of gutters

  • Resealed and top coated three common deck areas

  • Repaired concrete in the garage

  • Insulated Phase II garage ceiling

2007

  • Seal coated all three exterior stairwells

  • Renovated chimney stacks

  • Refurbished both elevators

2006

  • Exterminated bat infestation

2005

  • Repainted exterior of building

  • Installed new exterior railings

  • Re-carpeted all exterior walkways

  • New exterior lighting

2004

  • Resealed and top coated 1st floor and walkway

  • Repaired Phase I garage floor

2003

  • Replaced roof on building

  • Pool area was renovated

  • Re-carpeted office

2002

  • Connected Phase I storm drain to the Town of Vail’s storm drain system

1999

  • Plumbed building with natural gas for fireplaces and grills

  • Waterproofed exterior wall down to the footings in Phase II

1998

  • Painted exterior of building

  • Waterproofed and top coated common deck

1997

  • Re-carpeted Phase I walkways

1996

  • Replaced entrance driveway

1995

  • Re-carpeted Phase II walkways

1994

  • Painted exterior of building

  • Replaced exit driveway

1992

  • Repaired major leak in swimming pool

1990

  • Painted exterior of building

  • Topcoat and re-sealed first floor deck and walkway

1987

  • Installed enclosed stairwell emergency lighting

  • Major pool area renovation included two spas, new mechanical room and changing rooms and bather

1986

  • Repaired deteriorating fascia board on walkways

1985

  • Painted exterior of building

  • New signage for Vantage Point-Vail exterior

1984

  • Installed fire alarm system in building for heat and smoke detection and pull boxes

1981

  • Remodeled the storage area in garage from storage to office rental space

1980

  • Installed new wood shake shingle roof

  • Installed lawn sprinkler system on property

1979

  • Landscaped 80% of the property including trees, timber wall beds, sod, flower beds, etc.